LAMPIRAN 5A1


                                      CONTOH 1: TERMA KLAUSA BAYARAN


               1.     THE  SUPPLY,  DELIVERY,  INSTALL, TESTING  AND  COMMISSIONING  OF
                      THE HARDWARE, SOFTWARE AND e-BUDGET SYSTEM


                      1.1  First  Payment  upon  acceptance  of  hardware,  software  and  completion  of

                             technical training being RM 380,484.00. Documents to be presented are:

                             (i)    Signed Commercial Invoice (original);

                             (ii)   Certificate  of  Acceptance  of  Hardware  and  Software  as  per
                                    Schedule No. 4;

                             (iii)   Certificate of Completion of Training as per Schedule No. 8; and
                             (iv)   A copy of signed LOA.


                      1.2    Second Payment upon successful of Provisional Acceptance Test (PAT)

                             of  e-Budget  System  being  RM200,000.00.  Documents  to  be  presented
                             are:


                             (i)    Signed Commercial Invoice (original); and

                             (ii)   Certificate  of  Provisional  Acceptance  Test  of  e-Budget  as  per
                                    Schedule No. 5A.


                      1.3    Final Payment upon successful Final Acceptance Test and completion of

                             User Training being RM 318,547.00. Documents to be presented are:

                             (iii)   Signed Commercial Invoice (original); and

                             (iv)   Certificate of Final Acceptance Test as per Schedule No. 5B.