LAMPIRAN 5A1
CONTOH 1: TERMA KLAUSA BAYARAN
1. THE SUPPLY, DELIVERY, INSTALL, TESTING AND COMMISSIONING OF
THE HARDWARE, SOFTWARE AND e-BUDGET SYSTEM
1.1 First Payment upon acceptance of hardware, software and completion of
technical training being RM 380,484.00. Documents to be presented are:
(i) Signed Commercial Invoice (original);
(ii) Certificate of Acceptance of Hardware and Software as per
Schedule No. 4;
(iii) Certificate of Completion of Training as per Schedule No. 8; and
(iv) A copy of signed LOA.
1.2 Second Payment upon successful of Provisional Acceptance Test (PAT)
of e-Budget System being RM200,000.00. Documents to be presented
are:
(i) Signed Commercial Invoice (original); and
(ii) Certificate of Provisional Acceptance Test of e-Budget as per
Schedule No. 5A.
1.3 Final Payment upon successful Final Acceptance Test and completion of
User Training being RM 318,547.00. Documents to be presented are:
(iii) Signed Commercial Invoice (original); and
(iv) Certificate of Final Acceptance Test as per Schedule No. 5B.
1